Dept. of Trans. PROGRESS Serial No. Contract No. 21-111-17-48 11-429804 PROGRESS PAYMENT VOUCHER %complete: %time: 92% 100% Location: Federal Project: 11-SD-15-R11.2/R31.5 NONE Progress payment No. 011 Payment period ending: 04-20-21 HMS CONSTRUCTION INC 2885 SCOTT ST VISTA CA 92081 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,434,810.01 301,388.30 2. a. Extra Work 33,114.18 24,538.80 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 3,467,924.19 325,927.10 5. Mobilization 195,431.00 0.00 6. Total Work Completed 3,663,355.19 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 3,663,355.19 325,927.10 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 325,927.10