Dept. of Trans. PROGRESS Serial No. Contract No. 20-204-15-04 11-430184 PROGRESS PAYMENT VOUCHER %complete: %time: 72% 45% Location: Federal Project: 11-SD-805-8.4/8.8 B1IM-805-1(640) Progress payment No. 017 Payment period ending: 07-20-20 FLATIRON WEST, INC. 16470 W. BERNARDO DR #120 SAN DIEGO CA 92127 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 10,540,779.56 1,387,072.73 2. a. Extra Work 517,179.65 4,817.38 b. Adustment Comp. 90,028.94 0.00 3. Materials on Hand 4. Earned Subject to Retention 11,147,988.15 1,391,890.11 5. Mobilization 1,700,000.00 0.00 6. Total Work Completed 12,847,988.15 7. Deductions -3,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 12,844,988.15 1,391,890.11 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,391,890.11