Dept. of Trans. PROGRESS Serial No. Contract No. 21-260-16-31 11-430184 PROGRESS PAYMENT VOUCHER %complete: %time: 97% 63% Location: Federal Project: 11-SD-805-8.4/8.8 B1IM-805-1(640) Progress payment No. 031 Payment period ending: 09-20-21 FLATIRON WEST, INC. 16470 W. BERNARDO DR #120 SAN DIEGO CA 92127 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 14,959,635.50 345,597.00 2. a. Extra Work 1,095,061.46 0.00 b. Adustment Comp. 995,490.96 -9,554.99 3. Materials on Hand 4. Earned Subject to Retention 17,050,187.92 336,042.01 5. Mobilization 1,700,000.00 0.00 6. Total Work Completed 18,750,187.92 7. Deductions -4,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 18,746,187.92 336,042.01 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 336,042.01