Dept. of Trans. PROGRESS Serial No. Contract No. 24-324-14-20 11-430244 PROGRESS PAYMENT VOUCHER %complete: %time: 68% 37% Location: Federal Project: 11-SD-125-9.3/13.0 B1NH-P125(21) Progress payment No. 012 Payment period ending: 11-20-24 HAZARD CONSTRUCTION ENGR LLC 10529 VINE ST LAKESIDE CA 92040 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 17,012,078.22 1,156,801.70 2. a. Extra Work 686,719.82 66,389.53 b. Adustment Comp. 561,640.25 147,240.00 3. Materials on Hand 293,694.35 132,523.83 4. Earned Subject to Retention 18,554,132.64 1,502,955.06 5. Mobilization 3,000,000.00 0.00 6. Total Work Completed 21,260,438.29 7. Deductions -222.95 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 21,553,909.69 1,502,955.06 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,502,955.06