Dept. of Trans. PROGRESS Serial No. Contract No. 25-111-18-14 11-430244 PROGRESS PAYMENT VOUCHER %complete: %time: 81% 51% Location: Federal Project: 11-SD-125-9.3/13.0 B1NH-P125(21) Progress payment No. 017 Payment period ending: 04-20-25 HAZARD CONSTRUCTION ENGR LLC 10529 VINE ST LAKESIDE CA 92040 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 21,725,117.02 1,523,527.67 2. a. Extra Work 2,318,009.62 1,207,932.15 b. Adustment Comp. 561,640.25 0.00 3. Materials on Hand 40,334.00 -185,043.28 4. Earned Subject to Retention 24,645,100.89 2,546,416.54 5. Mobilization 3,000,000.00 0.00 6. Total Work Completed 27,604,766.89 7. Deductions -5,222.95 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 27,639,877.94 2,546,416.54 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,546,416.54