Dept. of Trans. PROGRESS Serial No. Contract No. 24-110-13-48 11-430254 PROGRESS PAYMENT VOUCHER %complete: %time: 1% 3% Location: Federal Project: 11-SD-52-5.1/9.0 ACNH-P052(21) Progress payment No. 001 Payment period ending: 04-20-24 CSI-CJA A JOINT VENTURE 9685 VIA EXCELENCIA #200 SAN DIEGO CA 92126 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 807,998.00 807,998.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 807,998.00 807,998.00 5. Mobilization 6. Total Work Completed 807,998.00 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 807,998.00 807,998.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 807,998.00