Dept. of Trans. PROGRESS Serial No. Contract No. 25-325-14-10 11-430254 PROGRESS PAYMENT VOUCHER %complete: %time: 91% 51% Location: Federal Project: 11-SD-52-5.1/9.0 ACNH-P052(21) Progress payment No. 020 Payment period ending: 11-20-25 CSI-CJA A JOINT VENTURE 9685 VIA EXCELENCIA #200 SAN DIEGO CA 92126 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 47,699,638.65 361,430.85 2. a. Extra Work 1,278,875.89 109,397.85 b. Adustment Comp. 204,328.61 -2,164.58 3. Materials on Hand 0.00 -39,910.59 4. Earned Subject to Retention 49,182,843.15 428,753.53 5. Mobilization 5,389,275.65 0.00 6. Total Work Completed 54,572,118.80 7. Deductions -25,000.00 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 54,547,118.80 418,753.53 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 418,753.53