Dept. of Trans. PROGRESS Serial No. Contract No. 26-167-13-47 11-430254 PROGRESS PAYMENT VOUCHER %complete: %time: 97% 65% Location: Federal Project: 11-SD-52-5.1/9.0 ACNH-P052(21) Progress payment No. 025 Payment period ending: 05-20-26 CSI-CJA A JOINT VENTURE 9685 VIA EXCELENCIA #200 SAN DIEGO CA 92126 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 48,666,224.62 238,495.97 2. a. Extra Work 2,592,145.57 62,128.49 b. Adustment Comp. -278,187.98 0.00 3. Materials on Hand 4. Earned Subject to Retention 50,980,182.21 300,624.46 5. Mobilization 5,389,275.65 0.00 6. Total Work Completed 56,369,457.86 7. Deductions -42,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 56,327,457.86 300,624.46 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 300,624.46