Dept. of Trans. PROGRESS Serial No. Contract No. 25-054-13-00 11-430394 PROGRESS PAYMENT VOUCHER %complete: %time: 58% 44% Location: Federal Project: 11-SD-805-23.9/25.1 ACIM-805(1) Progress payment No. 011 Payment period ending: 02-20-25 GRIFFITH COMPANY 3050 E BIRCH ST BREA CA 92821 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 11,480,763.88 1,120,233.94 2. a. Extra Work 458,726.31 21,301.74 b. Adustment Comp. -4,725.88 0.00 3. Materials on Hand 196,853.12 -4,615.36 4. Earned Subject to Retention 12,131,617.43 1,136,920.32 5. Mobilization 1,320,000.00 0.00 6. Total Work Completed 13,254,764.31 7. Deductions -6,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 13,445,617.43 1,136,920.32 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,136,920.32