Dept. of Trans. PROGRESS Serial No. Contract No. 25-080-11-16 11-430394 PROGRESS PAYMENT VOUCHER %complete: %time: 70% 47% Location: Federal Project: 11-SD-805-23.9/25.1 ACIM-805(1) Progress payment No. 012 Payment period ending: 03-20-25 GRIFFITH COMPANY 3050 E BIRCH ST BREA CA 92821 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 14,340,959.17 2,860,195.29 2. a. Extra Work 473,062.34 14,336.03 b. Adustment Comp. -21,150.95 -16,425.07 3. Materials on Hand 621,379.46 424,526.34 4. Earned Subject to Retention 15,414,250.02 3,282,632.59 5. Mobilization 1,320,000.00 0.00 6. Total Work Completed 16,112,870.56 7. Deductions -11,000.00 -5,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 16,723,250.02 3,277,632.59 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 3,277,632.59