Dept. of Trans. PROGRESS Serial No. Contract No. 25-108-11-46 11-430394 PROGRESS PAYMENT VOUCHER %complete: %time: 76% 51% Location: Federal Project: 11-SD-805-23.9/25.1 ACIM-805(1) Progress payment No. 013 Payment period ending: 04-20-25 GRIFFITH COMPANY 3050 E BIRCH ST BREA CA 92821 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 15,918,190.80 1,577,231.63 2. a. Extra Work 493,109.17 20,046.83 b. Adustment Comp. -21,150.95 0.00 3. Materials on Hand 442,924.25 -178,455.21 4. Earned Subject to Retention 16,833,073.27 1,418,823.25 5. Mobilization 1,320,000.00 0.00 6. Total Work Completed 17,710,149.02 7. Deductions -11,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 18,142,073.27 1,418,823.25 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,418,823.25