Dept. of Trans. PROGRESS Serial No. Contract No. 25-141-11-11 11-430394 PROGRESS PAYMENT VOUCHER %complete: %time: 90% 55% Location: Federal Project: 11-SD-805-23.9/25.1 ACIM-805(1) Progress payment No. 014 Payment period ending: 05-20-25 GRIFFITH COMPANY 3050 E BIRCH ST BREA CA 92821 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 19,200,508.60 3,282,317.80 2. a. Extra Work 493,109.17 0.00 b. Adustment Comp. -21,150.95 0.00 3. Materials on Hand 0.00 -442,924.25 4. Earned Subject to Retention 19,672,466.82 2,839,393.55 5. Mobilization 1,320,000.00 0.00 6. Total Work Completed 20,992,466.82 7. Deductions -11,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 20,981,466.82 2,839,393.55 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,839,393.55