Dept. of Trans. PROGRESS Serial No. Contract No. 25-168-11-18 11-430394 PROGRESS PAYMENT VOUCHER %complete: %time: 97% 56% Location: Federal Project: 11-SD-805-23.9/25.1 ACIM-805(1) Progress payment No. 015 Payment period ending: 06-20-25 GRIFFITH COMPANY 3050 E BIRCH ST BREA CA 92821 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 20,898,535.15 1,698,026.55 2. a. Extra Work 701,415.58 208,306.41 b. Adustment Comp. -21,150.95 0.00 3. Materials on Hand 4. Earned Subject to Retention 21,578,799.78 1,906,332.96 5. Mobilization 1,320,000.00 0.00 6. Total Work Completed 22,898,799.78 7. Deductions -11,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 22,887,799.78 1,906,332.96 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,906,332.96