Dept. of Trans. PROGRESS Serial No. Contract No. 24-142-18-55 11-430434 PROGRESS PAYMENT VOUCHER %complete: %time: 56% 66% Location: Federal Project: 11-SD-8-12.9/14.6 B1IM-008-1(330) 11-SD-8-14.9/14.9 Progress payment No. 019 Payment period ending: 05-20-24 GRIFFITH COMPANY 1128 CARRIER PKWY AV BAKERSFIELD CA 93308 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 7,095,672.48 814,617.39 2. a. Extra Work 3,015,440.29 573,797.33 b. Adustment Comp. 3. Materials on Hand 60,400.00 -341,091.67 4. Earned Subject to Retention 10,171,512.77 1,047,323.05 5. Mobilization 1,100,000.00 0.00 6. Total Work Completed 11,211,112.77 7. Deductions -7,200.00 -7,200.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 11,264,312.77 1,040,123.05 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,040,123.05