Dept. of Trans. PROGRESS Serial No. Contract No. 24-326-10-39 11-430514 PROGRESS PAYMENT VOUCHER %complete: %time: 66% 89% Location: Federal Project: 11-SD-15-R31.3/R37.1 ACSB-154(210) Progress payment No. 022 Payment period ending: 11-20-24 SECURITY PAVING COMPANY INC 3075 TOWNSGATE RD #200 WESTLAKE VILLAGE CA 91361 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 27,295,606.95 879,442.81 2. a. Extra Work 757,438.99 7,275.90 b. Adustment Comp. 557,610.43 -185,295.69 3. Materials on Hand 2,151,256.98 182,590.29 4. Earned Subject to Retention 30,761,913.35 884,013.31 5. Mobilization 3,476,499.88 0.00 6. Total Work Completed 32,087,156.25 7. Deductions -570,966.67 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 33,667,446.56 874,013.31 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 874,013.31