Dept. of Trans. PROGRESS Serial No. Contract No. 25-168-15-23 11-430514 PROGRESS PAYMENT VOUCHER %complete: %time: 80% 100% Location: Federal Project: 11-SD-15-R31.3/R37.1 ACSB-154(210) Progress payment No. 028 Payment period ending: 06-20-25 SECURITY PAVING COMPANY INC 3075 TOWNSGATE RD #200 WESTLAKE VILLAGE CA 91361 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 30,583,746.78 840,146.75 2. a. Extra Work 927,362.38 0.00 b. Adustment Comp. 527,127.55 -30,482.88 3. Materials on Hand 1,231,951.69 -84,441.60 4. Earned Subject to Retention 33,270,188.40 725,222.27 5. Mobilization 3,476,499.88 0.00 6. Total Work Completed 35,514,736.59 7. Deductions -570,966.67 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions -250,827.51 -72,522.23 c. Reduction after 95% Comp. 9. Total pay to Contractor 35,924,894.10 652,700.04 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 652,700.04