Dept. of Trans. PROGRESS Serial No. Contract No. 25-234-09-20 11-430514 PROGRESS PAYMENT VOUCHER %complete: %time: 86% 100% Location: Federal Project: 11-SD-15-R31.3/R37.1 ACSB-154(210) Progress payment No. 030 Payment period ending: 08-20-25 SECURITY PAVING COMPANY INC 3075 TOWNSGATE RD #200 WESTLAKE VILLAGE CA 91361 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 32,309,068.65 505,403.47 2. a. Extra Work 1,972,746.41 931,574.64 b. Adustment Comp. 225,187.58 -138,495.50 3. Materials on Hand 985,139.20 -120,101.28 4. Earned Subject to Retention 35,492,141.84 1,178,381.33 5. Mobilization 3,476,499.88 0.00 6. Total Work Completed 37,983,502.52 7. Deductions -570,966.67 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions 0.00 355,184.72 c. Reduction after 95% Comp. 9. Total pay to Contractor 38,397,675.05 1,533,566.05 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,533,566.05