Dept. of Trans. PROGRESS Serial No. Contract No. 26-021-12-45 11-430514 PROGRESS PAYMENT VOUCHER %complete: %time: 91% 100% Location: Federal Project: 11-SD-15-R31.3/R37.1 ACSB-154(210) Progress payment No. 035 Payment period ending: 01-20-26 SECURITY PAVING COMPANY INC 3075 TOWNSGATE RD #200 WESTLAKE VILLAGE CA 91361 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 34,932,003.50 288,292.48 2. a. Extra Work 2,274,511.15 98,345.94 b. Adustment Comp. 226,111.47 -3,000.00 3. Materials on Hand 0.00 -270,697.86 4. Earned Subject to Retention 37,432,626.12 112,940.56 5. Mobilization 3,476,499.88 0.00 6. Total Work Completed 40,909,126.00 7. Deductions -1,480,050.00 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 39,429,076.00 102,940.56 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 102,940.56