Dept. of Trans. PROGRESS Serial No. Contract No. 20-204-15-46 11-430524 PROGRESS PAYMENT VOUCHER %complete: %time: 79% 32% Location: Federal Project: 11-IMP-98-39.6/45.2 NONE Progress payment No. 004 Payment period ending: 07-20-20 HAZARD CONSTRUCTION COMPANY PO BOX 229000 SAN DIEGO CA 92192-9000 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,568,806.83 254,913.60 2. a. Extra Work b. Adustment Comp. -294,638.58 -294,638.58 3. Materials on Hand 4. Earned Subject to Retention 3,274,168.25 -39,724.98 5. Mobilization 500,000.00 0.00 6. Total Work Completed 3,774,168.25 7. Deductions 0.00 291,237.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 3,774,168.25 251,512.02 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 251,512.02