Dept. of Trans. PROGRESS Serial No. Contract No. 20-323-19-22 11-430524 PROGRESS PAYMENT VOUCHER %complete: %time: 85% 99% Location: Federal Project: 11-IMP-98-39.6/45.2 NONE Progress payment No. 008 Payment period ending: 11-20-20 HAZARD CONSTRUCTION COMPANY 10529 VINE ST LAKESIDE CA 92040 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,875,491.43 -48,278.40 2. a. Extra Work 210,516.14 66,112.50 b. Adustment Comp. -300,286.06 4,825.83 3. Materials on Hand 4. Earned Subject to Retention 3,785,721.51 22,659.93 5. Mobilization 500,000.00 0.00 6. Total Work Completed 4,285,721.51 7. Deductions -7,800.00 68,278.40 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 4,277,921.51 90,938.33 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 90,938.33