Dept. of Trans. PROGRESS Serial No. Contract No. 23-111-18-49 11-430564 PROGRESS PAYMENT VOUCHER %complete: %time: 32% 49% Location: Federal Project: 11-SD-67-R6.0/24.4 NONE Progress payment No. 011 Payment period ending: 04-20-23 HANSON AGGREGATES PACIFIC SOUTHWEST LLC 4211 PONDEROSA AVE #C SAN DIEGO CA 92123 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 7,553,906.78 794,968.64 2. a. Extra Work 1,905,458.16 341,632.09 b. Adustment Comp. -21,000.00 0.00 3. Materials on Hand 1,028,636.95 -1,111,957.21 4. Earned Subject to Retention 10,467,001.89 24,643.52 5. Mobilization 2,664,655.00 0.00 6. Total Work Completed 12,103,019.94 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 13,131,656.89 24,643.52 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 24,643.52