Dept. of Trans. PROGRESS Serial No. Contract No. 23-360-14-59 11-430564 PROGRESS PAYMENT VOUCHER %complete: %time: 89% 84% Location: Federal Project: 11-SD-67-R6.0/24.4 NONE Progress payment No. 019 Payment period ending: 12-20-23 HANSON AGGREGATES PACIFIC SOUTHWEST LLC 4211 PONDEROSA AVE #C SAN DIEGO CA 92123 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 28,297,152.38 439,560.79 2. a. Extra Work 4,285,615.93 343,620.83 b. Adustment Comp. -112,736.20 0.00 3. Materials on Hand 767,510.99 0.00 4. Earned Subject to Retention 33,237,543.10 783,181.62 5. Mobilization 2,804,900.00 0.00 6. Total Work Completed 35,274,932.11 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 36,042,443.10 783,181.62 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 783,181.62