Dept. of Trans. PROGRESS Serial No. Contract No. 23-262-12-35 11-430644 PROGRESS PAYMENT VOUCHER %complete: %time: 43% 32% Location: Federal Project: 11-SD-905-12.0/12.0 ACNH-P905(25) Progress payment No. 009 Payment period ending: 09-20-23 SEMA CONSTRUCTION INC 42690 RIO NEDO #G TEMECULA CA 92590 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,084,708.73 569,543.47 2. a. Extra Work 64,141.11 0.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 2,148,849.84 569,543.47 5. Mobilization 591,539.14 0.00 6. Total Work Completed 2,740,388.98 7. Deductions -36,871.05 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 2,703,517.93 559,543.47 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 559,543.47