Dept. of Trans. SEMI-FINAL Serial No. Contract No. 25-164-07-38 11-430644 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 11-SD-905-12.0/12.0 ACNH-P905(25) Progress payment No. 028 Payment period ending: 03-10-25 SEMA CONSTRUCTION INC 1901 CAMINO VIDA ROBLE #100 CARLSBAD CA 92008 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 5,098,883.15 947.68 2. a. Extra Work 489,122.02 20,153.78 b. Adustment Comp. 98,312.25 0.00 3. Materials on Hand 4. Earned Subject to Retention 5,686,317.42 21,101.46 5. Mobilization 622,672.78 0.00 6. Total Work Completed 6,308,990.20 7. Deductions 0.00 36,871.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 6,308,990.20 57,972.46 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 57,972.46