Dept. of Trans. PROGRESS Serial No. Contract No. 25-294-15-44 11-431274 PROGRESS PAYMENT VOUCHER %complete: %time: 36% 20% Location: Federal Project: 11-SD-5-R0.3/R36.0 NONE Progress payment No. 007 Payment period ending: 10-20-25 KIEWIT INFRASTRUCTURE WEST CO. 4650 BUSINESS CENTER DR FAIRFIELD CA 94534 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 20,268,690.21 4,440,596.40 2. a. Extra Work 383,004.25 365,209.75 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 20,651,694.46 4,805,806.15 5. Mobilization 8,078,257.55 0.00 6. Total Work Completed 28,729,952.01 7. Deductions -581,424.43 -8,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 28,148,527.58 4,797,806.15 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 4,797,806.15