Dept. of Trans. PROGRESS Serial No. Contract No. 25-017-14-12 11-432474 PROGRESS PAYMENT VOUCHER %complete: %time: 88% 33% Location: Federal Project: 11-SD-5-R52.3/R52.3 NONE Progress payment No. 005 Payment period ending: 11-27-24 ROVE ENGINEERING INC PO BOX 2108 EL CENTRO CA 92244 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 4,250.00 0.00 2. a. Extra Work 731,500.16 152,777.69 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 735,750.16 152,777.69 5. Mobilization 6. Total Work Completed 735,750.16 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 735,750.16 152,777.69 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 152,777.69