Dept. of Trans. PROGRESS Serial No. Contract No. 25-163-14-23 11-432674 PROGRESS PAYMENT VOUCHER %complete: %time: 8% 10% Location: Federal Project: 11-SD-0-0.0 NONE Progress payment No. 002 Payment period ending: 06-11-25 SB GENERAL ENGINEERING INC PO BOX 1400 LAKESIDE CA 92040 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 315,027.72 36,893.65 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 315,027.72 36,893.65 5. Mobilization 6. Total Work Completed 315,027.72 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 315,027.72 36,893.65 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 36,893.65