Dept. of Trans. PROGRESS Serial No. Contract No. 26-022-13-02 11-4B0054 PROGRESS PAYMENT VOUCHER %complete: %time: 14% 69% Location: Federal Project: 11-SD-67-R3.9/R6.1 NONE Progress payment No. 004 Payment period ending: 01-20-26 GRIFFITH COMPANY - HENKELS & MCCOY JOINT VENTURE 3050 E BIRCH ST BREA CA 92821 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 378,228.27 69,497.93 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 378,228.27 69,497.93 5. Mobilization 3,426.95 0.00 6. Total Work Completed 381,655.22 7. Deductions 0.00 2,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 381,655.22 71,497.93 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 71,497.93