Dept. of Trans. SUPPLEMENTAL Serial No. Contract No. 26-040-12-30 11-4B0334 PROGRESS PAYMENT VOUCHER %complete: %time: 96% 98% Location: Federal Project: 11-SD-5-9.1/R16.1 NONE Progress payment No. 007 Payment period ending: 01-20-26 GRIFFITH COMPANY - HENKELS & MCCOY JOINT VENTURE 3050 E BIRCH ST BREA CA 92821 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,297,332.64 -5,675.28 2. a. Extra Work 55,934.29 5,335.00 b. Adustment Comp. 60,042.09 0.00 3. Materials on Hand 4. Earned Subject to Retention 2,413,309.02 -340.28 5. Mobilization 2,727.00 0.00 6. Total Work Completed 2,416,036.02 7. Deductions 0.00 170,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 2,416,036.02 169,659.72 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 169,659.72