Dept. of Trans. PROGRESS Serial No. Contract No. 23-331-11-34 11-4C0034 PROGRESS PAYMENT VOUCHER %complete: %time: 24% 8% Location: Federal Project: 11-SD-5-R0.9 NONE Progress payment No. 003 Payment period ending: 11-20-23 HAZARD CONSTRUCTION ENGR LLC 10529 VINE ST LAKESIDE CA 92040 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 318,715.00 252,542.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 318,715.00 252,542.00 5. Mobilization 151,050.00 71,550.00 6. Total Work Completed 469,765.00 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 469,765.00 324,092.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 324,092.00