Dept. of Trans. PROGRESS Serial No. Contract No. 23-111-19-23 11-4C0044 PROGRESS PAYMENT VOUCHER %complete: %time: 25% 22% Location: Federal Project: 11-SD-5-12.8/13.2 NONE Progress payment No. 003 Payment period ending: 04-20-23 LB CIVIL CONSTRUCTION INC 324 EAST VALLEY PKWY ESCONDIDO CA 92025 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 546,524.50 272,765.50 2. a. Extra Work 1,108.03 1,108.03 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 547,632.53 273,873.53 5. Mobilization 183,350.00 38,600.00 6. Total Work Completed 730,982.53 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 730,982.53 312,473.53 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 312,473.53