Dept. of Trans. PROGRESS Serial No. Contract No. 00-361-09-07 12-012634 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 96% 96% 12-ORA-5-39.9/41.5 Federal Project: ACIM-005-2(868) Progress payment No. 39 Payment period ending: 12-20-00 M C M CONSTRUCTION INC P O BOX 620 NORTH HIGHLANDS CA 95660 Escrow No. 01050 Total Estimate This Estimate 1. Contract Itms Without Mobil. 42,375,041.91 316,604.32 2.a. Extra Work 1,449,215.33 33,913.69 b. Adjustment Comp. 773,637.29 0.00 3. Materials on Hand 80,729.22 53,298.15 4. Earned Subject to Retention 44,678,623.75 403,816.16 5. Mobilization 4,768,359.00 0.00 6. Total Work Completed 49,366,253.53 7. Deductions -51,021.74 -10,000.00 8. a.Contract Retentions -2,233,931.19 -20,190.81 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 47,162,029.82 373,625.35 10. Reduction Amt to Escrow 11. Payment to Escrow 2,233,930.00 12. Net Pymt. this Estimate 373,625.35