Dept. of Trans. SEMI-FINAL Serial No. Contract No. 04-132-14-00 12-012634 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 12-ORA-5-39.9/41.5 Federal Project: ACIM-005-2(868) Progress payment No. 65 Payment period ending: 10-03-02 M C M CONSTRUCTION INC P O BOX 620 NORTH HIGHLANDS CA 95660 Escrow No. 01050 Total Estimate This Estimate 1. Contract Itms Without Mobil. 43,268,873.79 -20,809.37 2.a. Extra Work 2,325,379.84 13,341.73 b. Adjustment Comp. 1,916,828.66 0.00 3. Materials on Hand 4. Earned Subject to Retention 47,511,082.29 -7,467.64 5. Mobilization 4,768,359.00 0.00 6. Total Work Completed 52,279,441.29 7. Deductions -41,021.74 10,000.00 8. a.Contract Retentions -2,355,057.80 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 2,355,057.80 0.00 9. Total pay to Contractor 52,238,419.55 2,532.36 10. Reduction Amt to Escrow -2,352,510.00 0.00 11. Payment to Escrow 2,352,510.00 12. Net Pymt. this Estimate 2,532.36