Dept. of Trans. PROGRESS Serial No. Contract No. 01-268-09-52 12-0126C4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 38% 5% 12-ORA-5-38.6/39.9 Federal Project: STPL-6212(4) ER-6212(4) Progress payment No. 05 Payment period ending: 09-20-01 MARINA LANDSCAPE INC 1100 E KATELLA AVE ANAHEIM CA 92805 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 452,788.50 356,982.50 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 452,788.50 356,982.50 5. Mobilization 61,275.00 29,025.00 6. Total Work Completed 514,063.50 7. Deductions 8. a.Contract Retentions -25,597.13 -16,016.53 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 488,466.37 369,990.97 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 369,990.97