Dept. of Trans. PROGRESS Serial No. Contract No. 04-082-09-36 12-0126C4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 12-ORA-5-38.6/39.9 Federal Project: STPL-6212(4) ER-6212(4) Progress payment No. 28 Payment period ending: 03-20-04 MARINA LANDSCAPE INC 1100 E KATELLA AVE ANAHEIM CA 92805 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,162,153.00 4,518.00 2.a. Extra Work 27,009.94 -185.07 b. Adjustment Comp. 475.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 1,189,637.94 4,332.93 5. Mobilization 64,500.00 0.00 6. Total Work Completed 1,254,137.94 7. Deductions 8. a.Contract Retentions -59,481.90 -216.65 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,194,656.04 4,116.28 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 4,116.28