Dept. of Trans. PROGRESS Serial No. Contract No. 03-140-13-01 12-0126E4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 42% 10% 12-ORA-5-41.5/43.5 Federal Project: STPL-6212(5) ER-6212(5) Progress payment No. 05 Payment period ending: 05-20-03 BELAIRE WEST LANDSCAPE INC P O BOX 6270 BUENA PARK CA 90622 Escrow No. 02036 Total Estimate This Estimate 1. Contract Itms Without Mobil. 553,650.00 16,870.00 2.a. Extra Work 190,285.08 190,285.08 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 743,935.08 207,155.08 5. Mobilization 14,250.00 0.00 6. Total Work Completed 758,185.08 7. Deductions 8. a.Contract Retentions -37,872.09 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 720,312.99 207,155.08 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 207,155.08