Dept. of Trans. PROGRESS Serial No. Contract No. 01-057-08-03 12-013314 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 95% 64% 12-ORA-55-12.7/13.4 Federal Project: ACNH-X059(29) Progress payment No. 23 Payment period ending: 02-20-01 BRUTOCO ENGINEERING AND CONSTRUCTION INC P O BOX 429 FONTANA CA 92334 Escrow No. 01217 Total Estimate This Estimate 1. Contract Itms Without Mobil. 16,074,277.01 399,043.39 2.a. Extra Work 446,737.69 42,162.40 b. Adjustment Comp. 140,882.05 13,860.00 3. Materials on Hand 4. Earned Subject to Retention 16,661,896.75 455,065.79 5. Mobilization 1,925,000.00 0.00 6. Total Work Completed 18,586,896.75 7. Deductions -55,381.53 15,000.00 8. a.Contract Retentions -833,094.84 -22,753.29 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 17,698,420.38 447,312.50 10. Reduction Amt to Escrow 11. Payment to Escrow 833,090.00 12. Net Pymt. this Estimate 447,312.50