Dept. of Trans. PROGRESS Serial No. Contract No. 01-172-16-22 12-013314 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 99% 73% 12-ORA-55-12.7/13.4 Federal Project: ACNH-X059(29) Progress payment No. 28 Payment period ending: 06-20-01 BRUTOCO ENGINEERING AND CONSTRUCTION INC P O BOX 429 FONTANA CA 92334 Escrow No. 01217 Total Estimate This Estimate 1. Contract Itms Without Mobil. 16,979,872.11 37,215.40 2.a. Extra Work 541,616.65 24,629.26 b. Adjustment Comp. 400,004.35 40,675.95 3. Materials on Hand 4. Earned Subject to Retention 17,921,493.11 102,520.61 5. Mobilization 1,925,000.00 0.00 6. Total Work Completed 19,846,493.11 7. Deductions -65,381.53 0.00 8. a.Contract Retentions -896,074.66 -5,126.03 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 18,885,036.92 97,394.58 10. Reduction Amt to Escrow 11. Payment to Escrow 896,070.00 12. Net Pymt. this Estimate 97,394.58