Dept. of Trans. PROGRESS Serial No. Contract No. 00-207-07-13 12-013324 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 71% 51% 12-ORA-55-13.4/14.4 Federal Project: ACNH-P055(35) Progress payment No. 19 Payment period ending: 07-20-00 M C M CONSTRUCTION INC P O BOX 620 NORTH HIGHLANDS CA 95660 Escrow No. 01178 Total Estimate This Estimate 1. Contract Itms Without Mobil. 12,891,278.71 846,845.74 2.a. Extra Work 1,077,953.06 37,513.05 b. Adjustment Comp. -67,360.29 5,692.41 3. Materials on Hand 55,486.01 1,751.46 4. Earned Subject to Retention 13,957,357.49 891,802.66 5. Mobilization 2,178,000.00 0.00 6. Total Work Completed 16,079,871.48 7. Deductions -30,000.00 -10,000.00 8. a.Contract Retentions -697,867.87 -44,590.13 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 15,407,489.62 837,212.53 10. Reduction Amt to Escrow 11. Payment to Escrow 697,860.00 12. Net Pymt. this Estimate 837,212.53