Dept. of Trans. PROGRESS Serial No. Contract No. 00-235-10-49 12-013324 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 73% 54% 12-ORA-55-13.4/14.4 Federal Project: ACNH-P055(35) Progress payment No. 20 Payment period ending: 08-20-00 M C M CONSTRUCTION INC P O BOX 620 NORTH HIGHLANDS CA 95660 Escrow No. 01178 Total Estimate This Estimate 1. Contract Itms Without Mobil. 13,384,951.56 493,672.85 2.a. Extra Work 1,082,263.88 4,310.82 b. Adjustment Comp. -67,360.29 0.00 3. Materials on Hand 62,595.51 7,109.50 4. Earned Subject to Retention 14,462,450.66 505,093.17 5. Mobilization 2,178,000.00 0.00 6. Total Work Completed 16,577,855.15 7. Deductions -25,000.00 5,000.00 8. a.Contract Retentions -723,122.53 -25,254.66 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 15,892,328.13 484,838.51 10. Reduction Amt to Escrow 11. Payment to Escrow 723,120.00 12. Net Pymt. this Estimate 484,838.51