Dept. of Trans. PROGRESS Serial No. Contract No. 00-298-12-17 12-013324 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 78% 60% 12-ORA-55-13.4/14.4 Federal Project: ACNH-P055(35) Progress payment No. 22 Payment period ending: 10-20-00 M C M CONSTRUCTION INC P O BOX 620 NORTH HIGHLANDS CA 95660 Escrow No. 01178 Total Estimate This Estimate 1. Contract Itms Without Mobil. 14,460,276.47 355,865.26 2.a. Extra Work 1,090,032.55 121.61 b. Adjustment Comp. -66,966.62 0.00 3. Materials on Hand 50,830.56 -6,332.13 4. Earned Subject to Retention 15,534,172.96 349,654.74 5. Mobilization 2,178,000.00 0.00 6. Total Work Completed 17,661,342.40 7. Deductions -35,000.00 0.00 8. a.Contract Retentions -776,708.65 -17,482.74 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 16,900,464.31 332,172.00 10. Reduction Amt to Escrow 11. Payment to Escrow 776,700.00 12. Net Pymt. this Estimate 332,172.00