Dept. of Trans. PROGRESS Serial No. Contract No. 00-326-10-32 12-013324 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 79% 63% 12-ORA-55-13.4/14.4 Federal Project: ACNH-P055(35) Progress payment No. 23 Payment period ending: 11-20-00 M C M CONSTRUCTION INC P O BOX 620 NORTH HIGHLANDS CA 95660 Escrow No. 01178 Total Estimate This Estimate 1. Contract Itms Without Mobil. 14,731,281.57 271,005.10 2.a. Extra Work 1,112,180.70 22,148.15 b. Adjustment Comp. -66,966.62 0.00 3. Materials on Hand 46,579.64 -4,250.92 4. Earned Subject to Retention 15,823,075.29 288,902.33 5. Mobilization 2,178,000.00 0.00 6. Total Work Completed 17,954,495.65 7. Deductions -35,000.00 0.00 8. a.Contract Retentions -791,153.76 -14,445.11 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 17,174,921.53 274,457.22 10. Reduction Amt to Escrow 11. Payment to Escrow 791,150.00 12. Net Pymt. this Estimate 274,457.22