Dept. of Trans. PROGRESS Serial No. Contract No. 00-356-15-25 12-013324 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 81% 66% 12-ORA-55-13.4/14.4 Federal Project: ACNH-P055(35) Progress payment No. 24 Payment period ending: 12-20-00 M C M CONSTRUCTION INC P O BOX 620 NORTH HIGHLANDS CA 95660 Escrow No. 01178 Total Estimate This Estimate 1. Contract Itms Without Mobil. 15,028,856.63 297,575.06 2.a. Extra Work 1,114,361.97 2,181.27 b. Adjustment Comp. -66,966.62 0.00 3. Materials on Hand 48,348.64 1,769.00 4. Earned Subject to Retention 16,124,600.62 301,525.33 5. Mobilization 2,178,000.00 0.00 6. Total Work Completed 18,254,251.98 7. Deductions -35,000.00 0.00 8. a.Contract Retentions -806,230.03 -15,076.27 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 17,461,370.59 286,449.06 10. Reduction Amt to Escrow 11. Payment to Escrow 806,230.00 12. Net Pymt. this Estimate 286,449.06