Dept. of Trans. PROGRESS Serial No. Contract No. 01-024-11-51 12-013324 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 82% 68% 12-ORA-55-13.4/14.4 Federal Project: ACNH-P055(35) Progress payment No. 25 Payment period ending: 01-20-01 M C M CONSTRUCTION INC P O BOX 620 NORTH HIGHLANDS CA 95660 Escrow No. 01178 Total Estimate This Estimate 1. Contract Itms Without Mobil. 15,286,034.83 257,178.20 2.a. Extra Work 1,117,790.44 3,428.47 b. Adjustment Comp. -57,128.96 9,837.66 3. Materials on Hand 116,298.08 67,949.44 4. Earned Subject to Retention 16,462,994.39 338,393.77 5. Mobilization 2,178,000.00 0.00 6. Total Work Completed 18,524,696.31 7. Deductions -35,000.00 0.00 8. a.Contract Retentions -823,149.72 -16,919.69 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 17,782,844.67 321,474.08 10. Reduction Amt to Escrow 11. Payment to Escrow 823,140.00 12. Net Pymt. this Estimate 321,474.08