Dept. of Trans. PROGRESS Serial No. Contract No. 01-058-07-52 12-013324 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 82% 71% 12-ORA-55-13.4/14.4 Federal Project: ACNH-P055(35) Progress payment No. 26 Payment period ending: 02-20-01 M C M CONSTRUCTION INC P O BOX 620 NORTH HIGHLANDS CA 95660 Escrow No. 01178 Total Estimate This Estimate 1. Contract Itms Without Mobil. 15,415,694.51 129,659.68 2.a. Extra Work 1,122,151.54 4,361.10 b. Adjustment Comp. -54,789.84 2,339.12 3. Materials on Hand 156,807.60 40,509.52 4. Earned Subject to Retention 16,639,863.81 176,869.42 5. Mobilization 2,178,000.00 0.00 6. Total Work Completed 18,661,056.21 7. Deductions -45,000.00 -10,000.00 8. a.Contract Retentions -831,993.19 -8,843.47 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 17,940,870.62 158,025.95 10. Reduction Amt to Escrow 11. Payment to Escrow 831,990.00 12. Net Pymt. this Estimate 158,025.95