Dept. of Trans. PROGRESS Serial No. Contract No. 01-115-09-23 12-013324 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 85% 77% 12-ORA-55-13.4/14.4 Federal Project: ACNH-P055(35) Progress payment No. 28 Payment period ending: 04-20-01 M C M CONSTRUCTION INC P O BOX 620 NORTH HIGHLANDS CA 95660 Escrow No. 01178 Total Estimate This Estimate 1. Contract Itms Without Mobil. 15,968,446.73 362,187.28 2.a. Extra Work 1,132,395.17 7,500.90 b. Adjustment Comp. -54,789.84 0.00 3. Materials on Hand 117,411.29 -39,316.31 4. Earned Subject to Retention 17,163,463.35 330,371.87 5. Mobilization 2,178,000.00 0.00 6. Total Work Completed 19,224,052.06 7. Deductions -45,000.00 0.00 8. a.Contract Retentions -858,173.17 -16,518.60 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 18,438,290.18 313,853.27 10. Reduction Amt to Escrow 11. Payment to Escrow 858,170.00 12. Net Pymt. this Estimate 313,853.27