Dept. of Trans. PROGRESS Serial No. Contract No. 01-143-09-08 12-013324 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 87% 80% 12-ORA-55-13.4/14.4 Federal Project: ACNH-P055(35) Progress payment No. 29 Payment period ending: 05-20-01 M C M CONSTRUCTION INC P O BOX 620 NORTH HIGHLANDS CA 95660 Escrow No. 01178 Total Estimate This Estimate 1. Contract Itms Without Mobil. 16,432,443.79 463,997.06 2.a. Extra Work 1,142,589.60 10,194.43 b. Adjustment Comp. -47,752.39 7,037.45 3. Materials on Hand 93,081.40 -24,329.89 4. Earned Subject to Retention 17,620,362.40 456,899.05 5. Mobilization 2,178,000.00 0.00 6. Total Work Completed 19,705,281.00 7. Deductions -55,000.00 -10,000.00 8. a.Contract Retentions -881,018.12 -22,844.95 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 18,862,344.28 424,054.10 10. Reduction Amt to Escrow 11. Payment to Escrow 881,010.00 12. Net Pymt. this Estimate 424,054.10