Dept. of Trans. PROGRESS Serial No. Contract No. 01-172-14-38 12-013324 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 87% 83% 12-ORA-55-13.4/14.4 Federal Project: ACNH-P055(35) Progress payment No. 30 Payment period ending: 06-20-01 M C M CONSTRUCTION INC P O BOX 620 NORTH HIGHLANDS CA 95660 Escrow No. 01178 Total Estimate This Estimate 1. Contract Itms Without Mobil. 16,676,665.78 244,221.99 2.a. Extra Work 1,169,518.26 26,928.66 b. Adjustment Comp. -47,752.39 0.00 3. Materials on Hand 87,287.18 -5,794.22 4. Earned Subject to Retention 17,885,718.83 265,356.43 5. Mobilization 2,178,000.00 0.00 6. Total Work Completed 19,976,431.65 7. Deductions -55,000.00 0.00 8. a.Contract Retentions -894,285.94 -13,267.82 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 19,114,432.89 252,088.61 10. Reduction Amt to Escrow 11. Payment to Escrow 894,280.00 12. Net Pymt. this Estimate 252,088.61