Dept. of Trans. SUPPLEMENTAL Serial No. Contract No. 01-340-09-07 12-013334 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 89% 88% 12-ORA-55-14.4/15.6 Federal Project: ACNH-P055(38) Progress payment No. 32 Payment period ending: 11-20-01 M C M CONSTRUCTION INC P O BOX 620 NORTH HIGHLANDS CA 95660 Escrow No. 01242 Total Estimate This Estimate 1. Contract Itms Without Mobil. 13,213,365.63 18,778.50 2.a. Extra Work 336,753.27 50,121.83 b. Adjustment Comp. 93,636.65 0.00 3. Materials on Hand 16,984.27 0.00 4. Earned Subject to Retention 13,660,739.82 68,900.33 5. Mobilization 1,667,481.00 0.00 6. Total Work Completed 15,311,236.55 7. Deductions -11,711.22 8,399.91 8. a.Contract Retentions -683,036.99 -3,445.02 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 14,633,472.61 73,855.22 10. Reduction Amt to Escrow 11. Payment to Escrow 683,030.00 12. Net Pymt. this Estimate 73,855.22