Dept. of Trans. PROGRESS Serial No. Contract No. 02-141-08-58 12-013334 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 94% 75% 12-ORA-55-14.4/15.6 Federal Project: ACNH-P055(38) Progress payment No. 38 Payment period ending: 05-20-02 M C M CONSTRUCTION INC P O BOX 620 NORTH HIGHLANDS CA 95660 Escrow No. 01242 Total Estimate This Estimate 1. Contract Itms Without Mobil. 14,228,540.83 35,111.00 2.a. Extra Work 1,148,635.65 4,701.73 b. Adjustment Comp. 572,791.50 0.00 3. Materials on Hand 15,053.80 -2,713.92 4. Earned Subject to Retention 15,965,021.78 37,098.81 5. Mobilization 1,667,481.00 0.00 6. Total Work Completed 17,617,448.98 7. Deductions -11,711.22 0.00 8. a.Contract Retentions -798,251.09 -1,854.94 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 16,822,540.47 35,243.87 10. Reduction Amt to Escrow 11. Payment to Escrow 798,250.00 12. Net Pymt. this Estimate 35,243.87